This procedure describes how to define a new CA AutoSys Workload Automation (AutoSys) conversion project. You can analyze the complexity of the conversion project by viewing the assessment report.
Before you begin
Ensure the following:
To define a new CA AutoSys conversion project:
NOTE: Only standard calendar conversion is supported by the Control-M Conversion Tool. Cyclic and extended calendars require manual definition in the Control-M environment. For more information, see Job scheduling in Using Control-M.
The data is loaded into the Conversion Tool and in the Assessment Report window, a summary of the imported data appears. For more information, see Data evaluation.
The Run Conversion window appears.
For more information about running conversion, see Data conversion.
The Conversion Settings window appears.
NOTE: In the Validation phase, you can compare your scheduler's forecast report to the Control-M forecast report created during validation. To create the report, use any of the report parameter files below.
For more information on validation, see Data validation.