Validating data in the Validation Report

This procedure describes how to validate data in the Validation Report.

To validate data in the Validation Report:

  1. To validate a Smart folder, sub folder, or job, highlight the Smart folder, sub folder or job, right click and select Validate.

    If validated, all scheduled dates are marked Conv_Tool_Validate.

    NOTE: To validate or unvalidate any row, highlight the cell on the row you want to delete and from the Edit menu, select Validate/Unvalidate row.

  2. To validate a specific date, highlight the date, right-click the required cell and Select Validate.

    NOTE: To unvalidate any date, right click the required cell and select unvalidate, or click Conv_Tool_Unvalid, or from the Edit menu.

    You can also do one or more of the following actions:

Parent Topic

Validating a conversion project