The following table describes the General parameters in the Additional WLM Rules tab.
For more information, see Setting additional CA Unicenter WLM (TNG) rules
Parameter |
Description |
|---|---|
Date format |
Defines the WLM date format for your conversion project. |
Application/Sub-Application separator |
Defines a separator character that converts WLM grouping to Control-M hierarchy format. EXAMPLE: PROD#SET1 where the separator is #, the Control-M Application entity is set to PROD and the Sub-application is set to SET1 |
Resources |
Defines the following target Control-M resource types:
If you select Auto it automatically selects a target Control-M resource type. |
PRIOR handling |
Enables you to set the following conditions:
|
Condition date for Everyday job |
Sets the following options for the generated Control-M in or out condition dates for everyday jobs. NOTE: Only available when PRIOR handling is set to Prev.
NOTE: For both options, the predecessor job sets the out condition to Order Date. |
Keep active for |
Defines the maximum number of days a job can wait for execution after order date. Valid value: Integer between 1 and 99. This parameter influences Control-M jobs only if the WLM job definition BACKLOG value is set to YES. |
First day of the week |
Defines the first day of the week of your work environment. |